SYARIKAT LEAN HUP (LIEW BROTHERS) SDN BHD V. CHEOW CHONG THAI
HIGH COURT [KUALA LUMPUR]
CIVIL APPEAL NO 11-9-1987
MUSTAPHA HUSSAIN, J
26 MAY 1988
CONTRACTS
Order accordingly.
Case referred to
Jervis v Howle and Talke Colliery Co Ltd [1937] Ch 67 (folld)
Legislation referred to
Housing Developers (Control and Licensing) Act 1966
Housing Developers (Control and Licensing) Regulations 1982, Schedule E, cl
19
Specific Relief Act 1950 s 30
Wilfred Abraham (S Santhana Dass with him) for the appellants.
SK Lingam for the respondent.
Solicitors: Abdul Raman Saad & Associates; SK Lingam & Co. Reported by PS
Ranjan
The appellants are housing developers of a housing project known as Taman
Permai Jaya in Mantin, Negeri Sembilan. The respondent is a purchaser of one
of the houses, lot no 5644, built by the appellants for the sum of $48,000.
Both the appellants and the respondent entered into a sale and purchase
agreement on 30 July 1982, which is subject to and in compliance with the
Housing Developers (Control and Licensing) Act 1966 and the rules and
amendments thereto.
Clause 12 of the said sale and purchase agreement states that the building (ie
the house) shall be completed and be ready for delivery of vacant possession
to the purchaser (ie the respondent here) within eighteen (18) months from
the date of the agreement and that if the said house is not completed and
ready for delivery of vacant possession to the purchaser within the
aforesaid period, then the developers (ie the appellants) shall pay to the
purchaser (respondent) agreed damages calculated from day to day at the rate
of 8% pa on the purchase price of the house from the date due for delivery
of vacant possession to the date of actual delivery of vacant possession.
At the trial before the magistrate, the respondent gave evidence. The
respondent agreed that she received a letter from the appellants dated 20
September 1984 stating that the house had been completed and asking her to
collect the keys to the house. But there was no certificate of fitness for
occupation and the road and drain had not been completed at the time she
received the letter from the appellants.
The road and drain were only completed in February 1986. The respondent
claimed damages at 10% (not at 8% as stated in the agreement) from 30
January 1984 to February 1986 (30 January 1984 is the 18 months' completion
date calculated from 30 July 1982, the date of signing of the agreement.
Actually the 18 months' period from 30 July 1982 ends on 29 January 1984).
The parties when they drew up the agreement were not aware that the damages
for late delivery of vacant possession have to be at 10% and not at 8% pa,
calculated on a day to day basis. So too was the completion period which
would be 24 months and not 18 months. This is in accordance with the Housing
Developers (Control and Licensing) Regulations 1982, which came into force
on 1 June 1982. The agreement herein between the parties was entered into
some two months later on 30 July 1982 and how on earth the appellants
(developers) were not aware of this is beyond comprehension as the agreement
was signed before a lawyer.
But it was the clear intention of both parties to comply with the provisions
of the relevant law ie the Housing Developers (Control and Licensing) Act
1966, and the Regulations made thereunder. This is beyond peradventure, a
mutual mistake of law, and ss 30 to 33 of the Specific Relief Act 1950 would
therefore come into operation.
It is clear law that if there is a mutual mistake, the terms of the contract
have to be rectified to comply with the law. Had both parties been aware of
the law, the agreement would have stipulated the damages for late delivery
of vacant possession as 10% of the purchase price instead of 8% and the
period for completion would have been stated as 24 months instead of 18
months, assuming the appellants/developers as shrewd developers would
certainly take advantage of the law. Anyway it was the intention of both
parties to enter into the agreement that conformed to the law.
Even though the respondent had not specifically pleaded for rectification of
this mistake of law in the agreement, the court in its discretion may order
rectification to express what both parties intended (see Jervis v Howle and
Talke Colliery Co Ltd [1937] Ch 67). Section 30 of the Specific Relief Act
1950, speaks of:
When, through fraud or a mutual mistake of the parties, a contract or other
instrument in writing does not truly express their intention, either party,
… may institute a suit to have the instrument rectified: … the court may in
its discretion rectify the instrument so as to express that intention,…
Accordingly, the sale and purchase agreement is hereby rectified to make it
comply with the provisions of the Housing Developers (Control and Licensing)
Regulations 1982 reg 12 and schedule 'E'. The damages for late delivery of
vacant possession of the house will therefore be 10% of the purchase price
and the period of completion 24 months from the date of entering into the
agreement. The day to day damages will therefore have to be calculated from
29 July 1984 to date of delivery of vacant possession.
What is then the date of delivery of vacant possession? We must not be
confused with the issuance of the certificate of fitness for occupation as
these two are separate matters. Clause 19 of schedule E to the Housing
Developers (Control and Licensing) Regulations 1982, makes it clear that
upon issue by the vendor's architect of a certificate certifying that the
construction of the said building (the house) has been duly completed and
the purchaser having paid all the moneys payable … 'the vendor shall let the
purchaser into possession …'
There is a proviso to this cl 19, which says that such possession shall not
give the purchaser the right to occupy and the purchaser shall not occupy …
'until such time as the certificate of fitness for occupation is issued'.
Thus, a distinction is made between vacant possession and the issuance of
the certificate of fitness for occupation.
According to the respondent, when she received the letter dated 20 September
1984 from the appellants, the developers, there was no certificate of
fitness for occupation, no electricity and no water supply. The drain and
road work was only completed in February 1986, and at the time of trial (18
September 1986) there was still no certificate of fitness for occupation
issued. But under cross-examination, the respondent agreed that the driveway
to the house was completed, so was the drain around the house. She did
collect the keys to the house ten days after receiving the letter dated 20
September 1984 from the appellants. The main outlet drain and the access
road had not been completed at that time.
The question now is when was this 'delivery of vacant possession'?
The appellants in their defence agreed that the main access road was
completed in September 1984, the water and electricity mains were supplied
on 20 February 1986, but at the time of writing the letter dated 20
September 1984, only the internal wiring and piping with the drains around
the house and the driveway were completed. The contention of the appellants,
the developers, is that delivery of vacant possession does not include the
electricity and water connections to the house itself and it does not also
include the main access road to the house.
An architect who gave evidence as a witness for the appellants in the court
below stated that certification of practical completion means that the unit
or house is completed and can be delivered. He further stated that the unit
or house need not have the road outside and also the drain outside for
practical completion, ie the infrastructure. The infrastructure was only
completed on 22 September 1984.
An engineer too gave evidence on behalf of the appellants, who said that the
access road was completed only on 22 September 1984.
It is common ground that the practical completion of the house was on 22
September 1984, that is, by then the access road, the drain around the
house, the internal wiring and internal laying of water pipes were 100%
completed.
The water and electricity supplies were only connected to the house on 20
February 1986.
According to the appellants, the date of practical completion of the house
was 22 September 1984 and it was never claimed that this practical
completion was the date of vacant possession. Looking at the third schedule
under cl 4(1) of schedule E, which the parties have to comply with, item 3
states: 'On handing over of vacant possession and connection of water and
electricity supply to the building' the purchaser will have to pay 95% of
the purchase price leaving only 5% to be held by the vendors' (in this case
appellants') solicitors as stakeholder, practically the full payment as far
as the purchaser (the respondent) is concerned.
It is therefore clear that vacant possession has to include the connection
of water and electricity, otherwise this item of connection of water and
electricity would have been separated and shown as another item under cl
4(1) of schedule E. The sale and purchase agreement entered into between the
appellants and the respondent will have to be rectified and read to conform
with the terms of the third schedule.
The certificate of fitness for occupation is not in issue as it is distinct
and separate from the issue of vacant possession as provided for under cl 19
of schedule E. In any event, the connection of water supply and electricity
does not make the house fit for occupation. There are thousands of squatter
huts which cannot qualify for a certificate of fitness for occupation, but
still have water and electricity supplies. Nor, on the contrary, does the
issuance of a certificate of fitness for occupation mean there is supply of
water and electricity to the house, as one can see hundreds of houses do not
have water and electricity even after the certificates of fitness for
occupation had been issued. In fact, as in this instant case, according to
the evidence of the respondent, 'the CF is not given to me till today' (ie
the date of hearing of the case on 18 September 1986). Yet, there was
connection of water and electricity on 20 February 1986. It is clear that
the certificate of fitness is not a sine qua non for connection of water and
electricity, though normally the water and electricity will only be
connected after the issuance of the certificate of fitness for occupation.
Looking at the evidence, 20 February 1986 is the date on which the water and
electricity supplies were connected to the house, and in the view of this
court, this is the date of 'delivery of vacant possession', if one reads the
terms in the third schedule under cl 4(1) of schedule E, item 3.
The appellants' witness in the court below had admitted that when the
appellants called the respondent to hand over the keys on 20 September 1984,
there was only what they themselves called 'practical completion' of the
house. They did not even dare to use the phrase 'vacant possession'.
The 24 months for delivery of vacant possession of the house under the
Housing Developers (Control and Licensing) Act 1966, from the date (30 July
1982) of execution of sale and purchase agreement should expire on 29 July
1984, and in view of the finding of this court that the date of delivery of
vacant possession in this case was 20 February 1986, damages shall be
calculated for the period 29 July 1984 to 20 February 1986, that is 569
days, at 10% of $48,000 which will work out to $7,482.74 with interest at 8%
pa on this sum from 20 February 1986 till date of satisfaction.
The appeal is therefore dismissed with costs.
|