Upholding purchaser protection
      02/08/2003
        NST-PROP
         By Salleh Buang
       
      There is a recent case regarding purchaser protection (the primary 
      objective of the Housing Development Act 1966) which merits close study by 
      everybody involved in the local housing industry. Although it is merely a 
      High Court decision (and not one handed down by the highest court in the 
      land), we must not forget that most of our cases on housing law are from 
      the High Court.
      
      The reason is pretty obvious. Not many developers want to spend more money 
      than necessary on the legal fees and court costs to take a case up the 
      judicial hierarchy and appeal a decision, especially since the new judgement could go either way. As any good litigation lawyer will advise, 
      when you go to court, there is no guarantee of a win, even if you think 
      you have a solid case.
      
      The case I want to refer to is that of Hariram a/l Jayaram & 14 Ors v 
      Sentul Raya Bhd [2003] 1 AMR 42, which Justice Abdul Malik Ishak, decided 
      on in Jan 21, 2002, but was only reported in our local law journal a year 
      later. 
      
      The facts can be summarised as follows:
      
      The 15 plaintiffs had purchased condominium units from developer Sentul 
      Raya Bhd (the defendant) using standard Sale and Purchase Agreements 
      (SPAs) as stipulated in Schedule H of the Housing Development (Control & 
      Licensing) Regulations 1989. 
      
      Under the agreement, the units were to be completed within 36 months, 
      failing which the developer would have to pay liquidated damages. Under 
      Clause 7 of the SPA, time was stated to be of the essence in the contract.
      
      Unfortunately, the defendant failed to deliver vacant possession of the 
      units on the stipulated date. It also failed to complete the common 
      facilities in the project. 
      
      As a result, the plaintiffs sued for liquidated damages.
      
      The defendant adopted several strategies to extricate itself out of its 
      predicament. For instance, it argued that the plaintiffs should have first 
      given the company “proper and express notices of termination” as required 
      under sect. 56 of the Contracts Act if they wished to avoid the contract. 
      The company further argued that since the plaintiffs had failed to do so, 
      the defendant was entitled to assume that the plaintiffs had waived their 
      option to avoid the contract, and that since no fresh time for completion 
      had been fixed, time was no longer the essence of the contract.
      
      The defendant also raised sect. 47 of the Contracts Act, which it said 
      allowed the company a leeway to complete the project within a reasonable 
      time. That being so, the defendant contended it was not obliged to pay any 
      liquidated damages to the plaintiffs.
      
      The defendant further maintained that since the plaintiffs had not given 
      any notice of their intention to accept a later performance of the 
      agreement as specified under sect. 56(3) of the Contracts Act, they were 
      not entitled to claim compensation for the delay.
      
      Finally, the defendant said that Schedule H is part and parcel of the 1989 
      Regulations and that being so, it is merely a piece of subsidiary 
      legislation. As such, it cannot override the general application of the 
      Contracts Act (which is a primary legislation).
      
      Admittedly, it was a clever way of interpreting the law. However, if we 
      are to cherish the stated objective of the Housing Development Act as 
      repeatedly recognised and upheld by our courts, we would probably detect a 
      hollow ring in the defence. I am glad that the learned trial judge saw 
      through it and had no difficulty rejecting it completely.
      
      He began his judgement by making two short sentences. “This was an 
      interesting case. I was told that I am breaking new ground.” 
      
      But shortly thereafter, he went straight into the morass of the law, which 
      only seasoned lawyers will comprehend. I will, instead, pick and choose 
      the relevant bits and pieces which can be understood and speedily digest.
      
      The learned judge said (in page 59 of the report) that the 1966 Act is “a 
      specific piece of social legislation to protect house buyers or purchasers 
      from unscrupulous developers”. He cited several established authorities, 
      including my favourite - Tun Suffian’s judgement in SEA Housing 
      Corporation Sdn Bhd v Lee Poh Choo [1982] 2 MLJ 31, which incidentally is 
      also cited in my book Malaysian Law on Housing Developers (Sweet & Maxwell 
      Asia, 2002).
      
      In contrast to that, the learned judge said (in page 61) that the 
      Contracts Act 1950 “is a piece of legislation of a general nature setting 
      out the general law governing contracts between the parties in general”. 
      Reiterating that the 1966 Act “is a specific legislation governing the 
      sale of houses by a licensed developer”, the judge pointed out that the 
      plaintiffs’ claims for liquidated damages in this case “were not based on 
      the general contract but rather on the standard Sale and Purchase 
      Agreements as set out in accordance with Schedule H ….”
      
      Seen in its “correct perspective”, the judge added, the case is “a tussle 
      between the specific law and the general law”. After considering several 
      authorities on the point, the judge summed up (in page 64 of the report) 
      that the 1966 Act “must take precedence” over the Contracts Act 1950 and 
      the SPAs signed by the plaintiffs “must be given effect accordingly”.
      
      Going a bit into the realm of statutory interpretation, the judge 
      explained that “it is axiomatic that in interpreting the specific piece of 
      social legislation at hand, an interpretation must be arrived at so as to 
      advance the object and purpose” of the 1966 Act. Full effect must be 
      accorded to “the avowed social objective” of that Act.
      
      Midway in his judgement for the plaintiffs, the judge said (in page 66) 
      that “it would certainly be erroneous in the extreme to burden the 
      plaintiffs as purchasers with the requirement of sect. 56(3) of the 
      Contracts Act” when the 1966 Act and the 1989 Regulations “do not impose 
      such a burden”. Consequently, the judge ruled that any attempt to impose 
      such a burden “will taint and remove the very protection” which the law 
      provides for purchasers.
      
      If you’re wondering why the defendant in the case did not just pay up 
      (after perhaps offering to pay 60 to 70 per cent of the plaintiffs’ 
      claim), I have to point out that the total penalty for late delivery was a 
      staggering RM1.5 million. It was the usual case of a defendant buying 
      time; having nothing to lose and everything to gain. It was the usual case 
      of wearing out the enemy; of forcing the purchasers to suffer the long 
      wait before their case could finally be heard and disposed of by the local 
      courts. 
      
      Yes, it underscored that important objective of the law, as so beautifully 
      put by Tun Suffian more than two decades ago: that the 1966 Act is meant 
      to protect purchasers from unscrupulous developers, to whom purchasers’ 
      rights are sometimes viewed as unnecessary irritants on their way to their 
      bank.