|
“HOUSING
DEVELOPMENT ACT: WHO DOES IT PROTECT?”
By
Haji Salleh Buang
Working Paper presented at the National Housing Conference II: The Road
Ahead in Nation Building 6th November 2001, Sunway Pyramid
Convention Centre
PART ONE – LOOKING BACK AT THE “OLD
LAW”
-
THE PRINCIPAL ACT
1.1
The Housing Developers (Control and Licensing) Act 1966 (Act 118),
which has been renamed the Housing Development Act (once the recent
Amendment Bill becomes law) is not (as it is generally believed) a
comprehensive law governing the housing industry. It was passed by
Parliament with three objectives – one, to check abuses of the then infant
housing industry; two, to regulate the activities of housing developers;
and three, up to a limited point to protect house buyers (not necessarily
in that order).
1.2
The Act applies only to Peninsular Malaysia. It had not, since its
inception, been made applicable to Sabah and Sarawak, and the status quo
regrettably remains until today. The Act, too, does not apply to housing
activities undertaken by statutory bodies and co-operatives societies.
Fortunately, this oversight has been corrected by the recent Amendment
Bill.
-
SUBSIDIARY LEGISLATION
2.1
Apart from the principal Act, the housing legislation in Peninsular
Malaysia is contained in two other important regulations, namely the
Housing Developers (Control and Licensing) Regulations 1989, and the
Housing Developers (Housing Development Account) Regulations 1991. The
1989 Regulations were a marked improvement on the earlier 1982
Regulations, which itself had earlier repealed the Housing Developers
(Control and Licensing) Rules 1970.
2.2 The 1970 Rules, together with the 1966 Act, could be regarded as
laying the first “ground rules” affecting the local housing industry.
Prior to that, the industry was completely unregulated. Any RM2 company
can start a housing project (at times even without owning any piece of
property), put up its signboard on an empty piece of land, and immediately
start collecting booking fees from eager house buyers.
-
MAIN OBJECTIVE OF THE LAW
3.1
The main objective of the law, as had been judicially recognized
and enunciated in several cases (some of them are mentioned below), is “to
protect the interest of purchasers”. However, an amendment to the 1989
Regulations passed in 1994 (in force since August 1, 1994) has made house
buyers wonder whether the law has changed direction – from one primarily
protecting the purchaser’s interest to one of also “giving aid and
comfort” to the developers.
3.2
The 1994 amendment was passed to put to rest a judicial conflict
regarding the actual meaning of the developer’s duty to provide the
“connection of water and electricity supply to completed houses”. This
legislative answer to resolve a judicial conflict (which turned out to be
in favour of developers) has been regarded by some quarters as a step
backward in protecting housing purchasers.
3.3
A dark spot in the history of the industry was the huge
unprecedented number of abandoned housing projects towards the close of
1980s – some say it was principally due to mismanagement by the
developers, whilst others pointed out to the inadequacy of the law. This
unhappy series of events finally led to the passing of the 1991
Regulations (requiring the developers to maintain a special account),
which came into force on August 26, 1991.
-
SCOPE
OF THE 1966 ACT
4.1
The long title of the Act states that it is to provide “for the
control and licensing of the business of housing development” in the West
Malaysia and for matters connected therewith. The Act does not have a
Preamble – which is indeed a pity.
4.2
The term “housing development” is defined in section 3 of the Act
to mean the construction and sale of “more than four units of housing
accommodation”. In addition, it also includes the sale of “more than four
units of housing lots by the landowner or his nominee with the view of
constructing more than four units of housing accommodation by the
said landowner or his nominee” [Definition substituted by Act
A703, with effect from December 1, 1988].
4.3
Note the underlined words in the preceding paragraph, the effect of
which is quite obvious. If there is an agreement to sell a plot of land
and subsequently there is a separate construction agreement to build a
house on the said land, and both these agreements are executed by the same
entity with the purchaser (and house owner), the Act still applies. If the
vendor (under the sale and purchase agreement of the land) and the
construction company) engaged to build the house on the land) are
different entities, the Act does not apply. You do not have to be genius
to get around the law, as far as this definition is concerned.
Housing
Accommodation
4.4
The expression “housing accommodation” has been specifically
defined in the Act to include “any building tenement or messuage which is
wholly or principally constructed, adapted or intended for human
habitation or partly for human habitation and partly for business
premises….” In essence, therefore, the Act only applies to cases where a
housing developer is undertaking the development of at least five units of
“housing accommodation” – that is to say, complete housing units (houses,
flats, apartments) or partly houses and partly shop or offices.
4.5
Thus, if a developer were to build a three-storey building where
the ground floor is a flatted factory, the first floor is a shop premise
and the second (top) floor is an office, the project will not be governed
by the Act. Consequently, the purchaser of such properties will not be
protected. His position vis-à-vis the developer is governed purely on
contract law – to which “caveat emptor” applies. Here lies, as always, the
potential for abuse of the weaker party by the stronger party; the recent
report of the commercial project in Semabok, Malacca, is a case in point.
-
PROTECTING THE
PURCHASERS
5.1
In the leading case of SEA Housing Sdn Bhd v
Lee Poh Choo (1982) 2 MLJ 31 the purchaser sued the developer for
breach of contract and for delivery of the issue document of title (LDT)
to a house he had purchased from the developer, The house in question was
completed after 23 months, instead of 18 months as stated in Sale and
Purchase Agreement. The issue before the court was whether the developer
could be excused for the delay, due to acute shortage of building
materials, a state of affairs which was then public knowledge. The
developer had relied on Clause 32 of the agreement which purported to
exempt him if non-fulfillment of any terms of the agreement was caused by
circumstances beyond his control.
5.2
At the High Court, the trial judge held that the 1966 Act and the
1970 Rules were passed by the authorities to protect the interests of the
public and the developer could not contract out of the Rules. Upon appeal
to the Federal Court, the appeal was dismissed.
5.3
In Khaw Daw Yau v Kin Nam Realty Development
Sdn Bhd [1983] 1 MLJ 35,
where the developer had jumped the gun and sold some Bumi lots to non-Bumi
purchasers, V. C. George J. expressed similar sentiments when he said “The
scheme of the Housing Developers (Control and Licensing) Act 1966 and the
Rules of 1970 is to provide a measure of protection to purchasers of
housing accommodation to a housing development against unscrupulous
developers.”
6
MINISTERIAL DIRECTIONS
6.1
Section 11 of the Act is a good example of the principal
legislative intent of the 1966 Act – to protect the interests of the
purchasers. Under this section, whenever it becomes apparent to the
Controller of Housing (either through investigations or information) that
the developer has become unable to meet his obligations to his
purchasers, is about to suspend his building operations or is carrying on
his business in a manner detrimental to the interests of his purchasers,
the Minister is empowered by law to give several directions to the
housing developer or take such other measures as he may deem necessary.
These directions, when given, must be complied with.
6.2
The directions which the Minister can issue under this provision
include:
·
Directing the developer to rectify or resolve any matter or
circumstances;
·
Appointing a person to advise the developer in the conduct
of his business;
·
Appointing a company to assume control and carry on the
business of the developer upon such terms and conditions as the Minister
may determine (with the concurrence of the Minister of Finance);
·
Directing the developer to present a petition to the High
Court for the winding up of his business; or
·
Taking such other actions as the Minister may consider
necessary.
The question which has
been repeatedly raised is whether the Minister has fully invoked section 11 of the
Act in the past when there were definite signs that developers were facing
difficulty in continuing or completing their projects. In many cases,
regrettably, actions taken were either too little or too late. If section
11 of the Act had fully enforced or invoked by the Ministry of
Housing and Local Government, probably the scale of abandoned housing
projects in the 1980s would not have reached such catastrophic
proportions.
6.3
Section 12 of the Act states that the Minister may give a housing
developer such directions as he considers fit and proper for purpose of
ensuring compliance with the Act. Such directions (which shall be given in
writing) are binding on the licensed developer – in other words, they must
be complied with by the developer to whom such directions had been given.
Unfortunately, despite the apparently wide scope of the provisions, the
courts have places a narrow interpretation on it.
6.4
In Public Prosecutor v Anamaly all Narayanan
[1989] 1 MLJ 45, the issue before the Seremban High Court was whether the
Minister is empowered under Section 12 of the Act to issue a ‘direction’
to the developer to make refunds to 16 purchasers. The developer in this
case had failed to start his housing project and the distressed purchasers
had demanded the refund of their payments. When the developer refused or
failed to do so, the purchasers had sought the assistance of the Minister.
The Minister had directed the developer, pursuant to his powers under
Section 12 of the Act, to refund the purchasers’ payments. When the
developer still failed to do so, he was brought to court to face criminal
charges. Mustapha Hussain J. held that the Minister had no such power to
order the developer to refund the purchasers’ money. The Public Prosecutor
did not appeal.
6.5
In April 1997, an unlicensed developer in Kulim, Kedah had been
collecting “booking fees’ from several would-be purchasers. While such
actions are clearly illegal under the law and the fraudulent developer
could be hauled to court to face criminal charges and, upon conviction, be
punished accordingly; this would not be of much help to the purchasers who
wish to get their money back. If the purchasers were to seek the
Minister’s help (as in Seremban case) to get their refund from the
developer, the end result would probably be the same. The Minister would
be powerless to act under section 12 to assist them.
6.6
Since the decision of the Seremban High Court has never been
overruled in any subsequent cases, it must be regarded as good law.
Regrettably, to my knowledge, no action had been taken by the Ministry
since then to amend the section. If a similar situation were to arise in
the future, the Minister would continue to be powerless to assist housing
purchasers. [Further comment – Annamaly is only High Court
decision. A similar case filed before another High Court Judge will not
necessarily end the same way, as one High Court Judge does not bind
another].
7
LICENSING OF DEVELOPERS
7.1
A housing developer must be in possession of a valid licence issued
under the Act before he undertakes any housing development; section 5 (1).
A licence is required for each housing development. Where a housing
development is to be undertaken in phases, a licence is required for each
and every phase of such housing development: see Regulation 3 (5) of the
1989 Regulations. Any misrepresentation of the information furnished by
the developer in its application for the licence or for a renewal of the
licence is an offence under the Regulations: see Regulations 3(2) and 4(4)
respectively.
7.2
There are stringent conditions imposed under the 1966 Act which
must be complied with before an applicant can be granted a licence. No
licence will be granted unless the company has an issued and paid-up
capital in cash of not less than RM250-000 (if applicant is a company) or
has made a deposit with the Controller of not less than RM100, 000 in cash
or in the form of a bank guarantee if the applicant is a “person or a body
of persons” (in other words, a sole proprietorship or a partnership):
section 6(1) (a) and (b).
7.3
While the figure of RM250, 000 might be sufficient in late 1960s,
is it still realistic today? Will an incorporated company having that much
(that little) paid-up capital be able to undertake a medium-size housing
development – say, a project consisting of over 100 unit of terrace houses
covering a land area of 10 acres? Even worse, will a sole proprietorship
or a partnership having a minimum capital of RM100,000 be able financially
to undertake a medium size development as stated above? It would seem to
be only logical to raise the figure in section 6(1) (a) further – say to
RM1 million, and to repeal / expunge section 6(1) (b) from the statute
book. More discussion on this later. [More of this later, when we discuss
the recent Amendment Act].
7.4
The Act also requires that no member of the company or firm should
have been convicted of an offence involving fraud or dishonesty. However,
Section 6(2) empowers the Minister, in his absolute discretion, to waive
any or all of the conditions mentioned above. [More of this later, when we
discuss the recent Amendment Act].
7.5
In 1997, Palmex Industries Sdn Bhd was fined RM15,000, in default 6
months jail, by the Penang Sessions Court for undertaking a housing
project (“Pearl View”) without a licence in Tanjung Bungah, Penang. The
company was charged under section 5(1), punishable under section 18 of the
Act. In mitigation, the company said that it applied for a licence in
January 1995 but was only granted a licence in December. Pending the issue
of the licence, the company had cleared the area and put up fencing. (The
Star, 29 April 1997).
7.6
Unlicensed developers (and their bankers / financiers) should heed
the warning of Anuar Zainal Abidin J. in the case of Keng Soon
Finance Berhad v M.K. Retnam Holdings Sdn Bhd; Bhagat Singh
& 11 Ors. As Intervenors [1996]
3 AMR 3021. The effect of this case is that if a bank grants a loan to an
unlicensed developer, the loan is bad and the security offered is also
bad. If the housing developer defaults, the bank cannot recover the loan
by instituting foreclosure proceedings on the land.
7.7
For the latest decision on the same point (unlicensed developers),
see Arab Malaysia Finance Berhad v Chan Sai Mee
[2001] 2 AMR 1743 (the Venice Hill Condominium case).
8
DUTIES OF DEVELOPERS
8.1
The duties of a licensed developer under section 7 of the Act are
as follows –
(a)
Within four weeks of making any alterations in any of the documents
submitted to the Controller under section 5(3), he must furnish to the
Controller written particulars of such alterations.
(b)
He must exhibit, at all times, in a conspicuous position in any
office or branch office, a copy of his last audited balance sheet and the
names and particulars of each person who has the control and management of
the business of the company; [Under the new law, this paragraph has
been amended to include a copy of his developers’ licence, the
advertisement and the sale permit];
(c) He
must keep such accounting and other records as will sufficiently explain
the transactions and financial position of the company;
(d) He
must appoint auditors each year to carry out the annual audit;
(e)
Within three months of the close of the company’s financial
year, he must send to the Controller a copy of the auditor’s report
prepared under section 9 of the Act; [Under the new law, the period has
been enlarged to “six months];
(f) He
must submit a statement in the prescribed form to the Controller twice a
year not later than January 21 and July 21 of each year: [Under the new
law, the prescribed form includes a report of the progress of the housing
development]; and
(g)
He must forthwith inform the Controller where he considers that
he is likely to become unable to meet his obligations to the purchasers. [Under
the new law. this has been amended by the addition of the words “at any
stage of the housing development before the issuance of the certificate of
fitness for occupation].
[Note: the new law has also added new
paragraphs (h) to (k). More of this later, at paragraph 22.4 below]
8.2
These are onerous obligations indeed. The question is how thorough
and consistent had the Ministry been in enforcing these provision of the
law? The present Housing Minister had (soon after his appointment) openly
admitted that enforcement had been disappointing, if not altogether
non-existent. A news report quoted the Minister as saying that ‘developers
have taken the Ministry for granted”. The Minister made that surprising
remark after hinting that heavier penalties will be imposed to developers
who fail to submit their progress reports every 6 months (New Straits
Times, February 18, 2000).
9 OPEN
/ MAINTAIN HOUSING DEVELOPMENT ACCOUNT
9.1
Section 7A of the Act (a new provision inserted by Act 703 with
effect from December 1, 1988) requires the developer to open and maintain
a Housing Development Account. Under this provision, unless the developer
is implementing a “Build & Sell System”, he is required to open and
maintain a Housing Development Account with a bank or a financing company
for each housing development undertaken by him. The deadline for opening
the account was August 31, 1991.
9.2
If a housing project is developed in several phases, the developer
is required to open and keep an account for each phase of the project. The
developer is required to put into the account all payments received by him
from the sale of the housing accommodation in the project. The developer
is not allowed to withdraw from the account except as authorized by the
Housing Developers (Housing Development Account) Regulations 1991.
9.3
Section 7A was enacted specially to solve the problems of the 80s - developers who siphoned off
funds from projects (currently in progress) to other “ventures” including
for personal use and gratification. The Ministry stated that the
Regulations had been largely successful in putting a stop to this
unhealthy practice.
9.4
Section 7A does not apply if a housing developer implements a
“Build and Sell System”. While such a system clearly benefits the house
buyers (who can actually see and inspect the property before parting with
a single sen of the purchase price), not many developers, including public
sector agencies, are willing to implement this because not many financiers
are prepared to provide the necessary financing.
9.5
Under the new law, the penalties for contravening this section have
been increased – from a fine of RM10,000 to RM50,000 (lower limit) and a
fine of RM100,000 to RM500,000 (higher limit).
10
THE STANDARD SALE AND PURCHASE AGREEMENT (SPA)
10.1
Regulation 11 of the Housing Developers (Control and Licensing)
Regulations 1989 states:
(1)
Every contract of sale and purchase of a housing accommodation
together with the subdivided portion of land appurtenant thereto shall be
in the form prescribed in Schedule G and where the contract of sale is for
the sale and purchase of a housing accommodation in a subdivided building,
it shall be in the form prescribed in Schedule H.
(2)
No housing developer shall collect any payment by whatever name
called except as prescribed by the contract of sale.
10.2
The intention behind Regulation 11 is obvious. No housing developer
is allowed to “contract out” of his obligations under the law. No money
can be collected by the developer until the parties have signed the SPA
and thereafter further payments can only be collected in accordance with
the terms of the SPA. Regrettably, some people are still ignorant of the
law. As a result, there had been cases of housing developers collecting
“booking fees” from unsuspecting purchasers. Some of these developers had
not even obtained the necessary approvals from the relevant authorities
and the developer’s licence and advertising permit from the Ministry of
Housing and Local Government.
11 DEVELOPER’S DUTIES UNDER THE SPA
11.1
The duties of the developer under the standard SPA can be briefly
described as follows:-
(a)
To sell the property free from any restrictions and encumbrances
other than those conditions expressed or implied affecting the title;
(b)
Upon execution of the agreement, not to encumber the property save
with the prior approval of the purchaser; and to undertake that the
property shall be rendered free from any encumbrance immediately prior to
the handing over of vacant possession of the building to the purchaser;
(c)
To complete the construction of the house on time, as para 7 of the
standard SPA (see Schedule G and H) states that “Time shall be the
essence of the contract, in relation to all provisions of this Agreement”.
For standard housing units, the period of completion and handing over
vacant possession is 24 months (para 20 of Schedule G) while for
sub-divided buildings, the period is 36 months (para 24 of Schedule H);
(d)
To obtain the issuance of a separate document of title (para 10 of
Schedule G), and in the case of a sub-divided building, to obtain a
separate strata title (para 10 of Schedule H);
(e)
To execute a valid and registrable memorandum of transfer of the
property to the purchaser (subject to the payment of the purchase price by
the purchaser);
(f)
To construct the building in “good and workmanlike manner” in
accordance with the description set out in the Fourth Schedule to the
agreement and in accordance with the plans approved by the relevant
authorities;
(g)
To construct the infrastructure, including roads, driveways,
drains, culverts, water mains and sewerage plants serving the housing
project as a whole in accordance with the requirements and standards of
the relevant authorities, and to maintain and upkeep the same (with the
purchaser having to contribute to the costs of such upkeep) until they are
taken over by the relevant authorities;
(h)
To provide services, including refuse collection, cleaning of
public drains and grass cutting on the road reserves, from the time of
handing over of vacant possession until the same is taken over by the
relevant authorities (with the purchaser having to contribute a fair
proportion of the cost);
(i)
To lay all necessary water, electricity and sewerage mains to serve
the housing project, and to apply for the connection of internal water,
electricity, sanitary and gas installation (if any) of the building to the
mains – but not obliged to ensure that there is water and electricity
flowing into the building upon its completion (the effect of an amendment
in the Regulations in [1994].
(j)
To comply with “any written law for the time being in force” (a
number of developers have been taken to court for contravening several
provisions of the Environmental Quality Act 1974 and the Occupational
Safety and Health Act 1994);
(k)
To apply for certificate of fitness (CF) of occupation and, to
ensure that there shall be no delay in the issuance of such certificates,
the developer is required to “duly comply with the requirements” of the
relevant authorities;
(l)
To remedy defects, shrinkage and other faults during the defects
liability period (18 months after handing over vacant possession of the
building to the purchaser).
11.2
Whilst the good intentions of the legal draftsman (to provide
safeguards for the purchasers) cannot be denied, it is a pity that the SPA
is full of legal jargon. Much of the benefit is lost due to lack of
comprehension – resulting in purchasers not really being aware of the full
extent of their rights under the law. Shouldn’t’ the Housing Ministry come
out with a “simpler version” under the SPA, or at the very least, a
Handbook for Purchasers in layman’s terms?
12
DEVELOPER’S PRIVILEGE TO APPLY FOR EXTENSION
12.1
Regulation 11(3) gives a “dark side” of the above picture which
some purchasers are not aware of. This provision enables the developer to
apply to the Controller for extension of time to complete the project
beyond the period stipulated in the SPA or to “waive or modify” any
provision of the SPA. If the Controller is satisfied that “owing to
special circumstances or hardship or necessity” compliance with any
provision of the SPA “is impracticable or unnecessary”, he MAY, by a
certificate in writing, grant the extension requested or “waive or modify”
any such provision.
12.2
The proviso to this Regulation, however, stipulates that no such
application for “waiver or modification” shall be entertained if it is
made “after the expiry of the time stipulated for the handing over of
vacant possession” of the property to the purchaser.
12.3
What is particularly objectionable about this provision is that the
application for extension can be made by the developer to the Controller
without purchasers being notified and be informed of their right to
make representations against the developer’s application. However, the
Controller can, acting on his own initiative, inform the purchasers of the
developer’s application and hear their representations before making his
decision.
13
WATER AND ELECTRICITY SUPPLY
13.1 This
is one area where uncertainty in the law had led to a lot of pain and
suffering on the part of house
purchasers. Until the 1989 Regulations were amended in 1994 (effective
from August 1, 1994), there was some doubt to whether or not ‘completion”
means that water and electricity supply has been connected to the building
– in other words, whether water and electricity supply is actually
available on the premises. Judicial decisions on the matter have been
evenly divided.
A. Decisions in favour of purchasers
13.2
In Syarikat Lean Hup (Liew Brothers) Sdn Bhd v Cheow Chong
Thai [1988] 3 MLJ 21, Mustapha Hussin J. held that vacant
possession must include “the connection of water and electricity”. The
trial Judge’s decision was later upheld by the Supreme Court on April 19,
1989
13.3
In Kandasamy all Sreenivsagam v Syarikat Muzwina
Development Sdn Bhd [1990] 1 MLJ 15, Abdul Malek J. held that
vacant possession must include electricity and water. In Charles
Muriel (f) v Newacres Sdn Bhd [1994] 2 AMR 23:1145, the same issue
came before the Shah Alam High Court, upon hearing an appeal from the
decision of a Sessions Judge. Abu Mansor J. held that vacant possession
must include electricity and water.
13.4
In Hoya Holding Sdn Bhd v Chin Ting Hing & Anor
[1994] 3 AMR 48:2532 Abdul Malik
Ishak J. said “there must be water and electricity supplies actually
running through the internal waterpipes, electric lines and powerlines
in the dwelling house before the question whether or not vacant possession
has been delivered could be considered.”
The learned Judge added that “Malaysian
house buyers must surely insist and expect that the handing over of vacant possession of completed
houses can only be effected if and only if he water and electricity meters
have been installed and energized within the completed houses. This seems
to be the trend and thinking of the Malaysian Courts”.
B. Decision in
favour of developers
13.5
However, in Tay Ket @ Chan Kong Seong v Bumibaku Development
Sdn Bhd [1994] 2 AMR
35:1833, Wan Adnan J. expressed a different opinion. The judge held that
under the 1982 Regulations (the applicable law to the case), the developer
(defendant) had duly fulfilled its obligations as soon as the defendants
had energized the sub-station to enable electricity to be connected to all
the houses in the project. The trial Judge refused to follow Lean
Hup because the issue which he deliberated on (the energizing of the
sub-station) was “not canvassed” in that earlier case.
13.6
In Salmah binti
Sulalman & Anor. V Metroplex Development Sdn Bhd [1994] 3 AMR
47:2514, Siti Norma J. held that under the applicable law to the case –
Rule 12(1) (1) of the 1970 Rules – the developer’s obligations “is only
to connect the outside electricity and water mains to the internal
electricity and water mains and not to the flow of water and electricity
for which deposits had to be made to the appropriate authorities and there
may well be a delay in the tendering of such deposits, not to mention the
delay that may be caused by the authorities concerned in the actual supply
of such amenities.” On appeal to the Court of Appeal (see [1997] AMR
592), the trial Judge’s decision was upheld. Dismissing the purchaser’s
appeal, Zakaria Yatim JCA said that “We agree with Siti Norma Yaakob J
that the Rule speaks of connection of the electrical and water mains and
that the respondent’s obligation was only to connect electricity and water
mains to the internal electricity and water mains and not the flow water
and electricity.”
C. Stand taken
by Local Authorities
13.7 While the legal
uncertainty (and contradictory case-law) continues unresolved, the
purchasers’ problem was further aggravated by the stand taken by local
authorities that as long as the completed houses have not been issued with
certificates of fitness for occupation, connection of water and
electricity to the premises will not be permitted. In 1993, Selangor
Waterworks Department director Liew Wai Kiat was reported as saying that
water supply will not be connected to phase two of Taman Pandan Mewah houses in
Ampang until the certificates of fitness have been issued by the local
authorities. He was quoted as saying “The only way for them to get their
water supply is to produce the certificate of fitness” [New Straits
Times, December 28, 1993]
13.8
This unhappy state of affairs has made victims of innocent people.
Consider, for example, the plight of purchasers of low-cost flats in Taman
Muliajaya, Ampang Tasik, who had reportedly been left “high and dry” for
18 months after the developer had given them “vacant possession” of their
properties.” [Malay Mail, April 5, 1993].
D. Resolved in
favour of developers
13.9
This judicial uncertainty was finally resolved (for better or for
worse – depending upon where you stand) in the 1994 amendment. For housing
projects launched after the amendment came into force (August 1, 1994),
the developer is only required to ensure that water and electricity supply
is “ready for connection”. The phrase “ready for connection” has been
expressly defined in the amended regulations to mean as follows –
(a)
water and electrical fittings have been installed by the developer;
(b) the fittings have been tested
and commissioned by the appropriate authority; and
(c)
supply is available for tapping into individual homes.
13.10 While the amendment is welcomed in
having finally resolved the uncertainty,
the effect of the amendment can hardly be said to bring cheer or
joy to the purchasers.
14 CERTIFICATE
OF FITNESS OF OCCUPATION (CF)
14.1
This is another matter which has caused immeasurable anxiety and
distress to
house purchasers. The
applicable law is found in By-Law 25 of the Uniform Building By-Laws 1984,
a subsidiary legislation made under section 133 of the Street, Drainage
and Building Act 1974.
14.2
The local judiciary is generally in agreement that “The certificate
of fitness for occupation is … distinct and separate from the issue of
vacant possession …” (see
Syarikat Lean Hup (Liew Brothers) Sdn Bhd v Cheow Chang Thal
[1988] 3 MLJ 221).
14.3
In the old case of South East Asia Brickworks. Sdn Bhd v
Maria Antonette [1974] 2
MLJ 46, Abdul Hamid J. (as he then was) had said that “completion” does
not mean that the developer must have obtained a certificate of fitness
for occupation of the building. In the judge’s opinion, to do so would be
to import “a term which was not within contemplation of the parties and
would have the effect of frustrating the contract”.
14.4
In the light of the above, as far as the purchaser is concerned,
the legal position with regard to the completion of the house, vacant
possession and the issuance of certificates may be summed up as follows:
(a)
Within 24 months (or 36 months in the case of subdivided
buildings), the property bought by the purchaser must be completed by the
developer and handed over to the buyer. Keys must be given to the
purchaser. It does not follow that the purchaser can immediately occupy
the house, that is, not until and unless the CF has been issued by the
relevant local authority.
(b)
It was originally thought that water and electricity supply must
actually be connected to, and flowing in, the building when vacant
possession is handed over to the purchaser. Effective from August 1, 1994,
the legal uncertainty has been put to rest by a legislative amendment – in
favour of developers.
(c)
Everything that needs to be done by the developer must have been
done to comply with the requirements of the appropriate authority for the
issuance of a certificate of fitness. However, the developer is not
legally obliged to guarantee when the certificate of fitness will be
issued.
14.5
The problem for the purchaser is that, as long as the certificate
of fitness has not been issued by the relevant local authority, he cannot
legally occupy the house, even though in law he “is deemed” to have taken
delivery of the house.” This is where a serious mismatch occurs between
law and reality.
14.6
In one case at the end of 1993, some 100 house buyers of Bandar
Puchong Jaya still could not get their certificates of fitness because the
developer had not built an access road as outlined in the development
plan. What the developer did in this case was to upgrade an existing
temporary access road. [New Straits Times, December 9,
1993.]
14.7
Media reports in late 1993 highlighted the fact that some 200
buildings in Kuala Lumpur were issued with temporary certificates of
fitness. The question is – how temporary is temporary? Apparently,
in some cases the temporary certificates were renewed as many as six
times. Under By-Law 26(1), a temporary CF can last only for 6 months – and
even then, it can be issued “where only minor deviations from the approved
building plans had been made and pending full compliance with the
requirements” of the local authority.
14.8
Although local authorities had in the past been urged by the
Ministry of Housing and Local Government to issue temporary certificates
of fitness in certain cases which merit such an issuance, the Ministry
announced in 1997 that such a practice was to be discontinued. Developers
and purchasers believe that irrelevant conditions imposed by many local
authorities “have resulted in delayed issuance of certificates of fitness
for buildings throughout the country, preventing thousands of owners from
moving into their premises”.[New Straits Times, August 5,
1995].
Reasons for delay in issuance of CF
14.9
Delay in the issuance of CF had been attributed to several things –
e.g. non-completion of drainage and sewerage works and landscaping,
non-payment of development charges, unauthorized alterations and failure
to clear the site. In one case, the Hulu Langat District Council said it
would not issue a certificate of fitness to a condominium project until
the developer has satisfied the authorities that it has taken appropriate
“Safety measures” for the project. [Utusan Malaysia,
August 28, 1995].
14.10
There are also other reasons, which some developers had termed as
“irrelevant conditions” being imposed by the local authorities –
(a)
requirement of a Bumiputra quota;
(b)
developer to maintain sewerage system even after the issuance of
certificate of fitness;
(c)
developer to grow plants to a certain height; and
(d)
developer to carry out landscaping works.
Cabinet directive
14.11
On January 10, 1996, the Cabinet directed all local authorities to
issue CF within 14 day of a building having met all structural and legal
requirements. This directive followed a joint study by the Ministry of
Housing and Local Government and the Malaysian Modernisation and
Management Planning Unit (Mampu), which found that many house owners were
compelled to wait for indefinite periods for certificates of fitness even
though they had been given their keys by the developers.
14.12
Local authorities were encouraged to emulate the Kuantan Municipal
Council. In March 1997, the Housing Ministry confirmed that the Kuantan
local authority was able to issue CF within two days of the application –
provided all documents were in order.
15
PROPERTY FREE FROM ENCUMBRANCES
15.1
Under the earlier 1970 Rules, the developer was not allowed to
subject the land to encumbrances without the approval of the purchaser
after the SPA had been signed: rule 12(1)
(a) and (b). If the purchaser had given his approval, the developer
had to ensure that the land would be free from any encumbrances on the
date when vacant possession of the property was to be given to the
purchaser. These provisions are now contained in the schedule to the 1989
Regulations, in the form of a developer’s covenant to the purchaser.
Developer’s covenant
15.2
The covenant is divided into two parts. First, the
developer undertakes that after the execution of the SPA he will not
charge the land without any prior consent of the purchaser. Second,
assuming that he had obtained the purchaser’s consent and had then
charged the property, he must discharge it immediately before he is
required to deliver vacant possession of the property to the buyer.
15.3
The rule of prudence to be observed by a purchaser when buying
properties without titles (whether they are sited on terra firma or are
‘bungalows in the air’) is to ensure that the developer has a solid
reputation. The law reports are littered with many cases of purchasers
being left in the lurch by developers – their dream homes in shambles,
their precious investments down the drain. This happens when the developer
fails to proceed with the project as a result of which the bridging
financier then has no choice but to commence foreclosure proceedings.
When bridging financier forecloses
15.4
In mid 90s, however, there have been cases where the courts have
extended their protection to purchasers when the properties which they had
purchased became the subject matter of foreclosure proceedings commenced
by bridging financiers against the developers: see in particular the
decision of the Supreme Court in Kuching Plaza Sdn Bhd v Bank
Bumiputra Malaysia Bhd [1991] 3 MLJ 163, and following that the
decision (which went the other way) in James Edward Buxton & Anor v
Supreme Finance Bhd [1992]
1 AMR 81. These cases, however, must be seen in their proper light. They
represent the exception, rather than the norm.
16 DEVELOPER’S CONSENT TO DEED OF ASSIGNMENT
16.1
Not infrequently purchasers of parcels in sub-divided buildings (as
well as purchasers of conventional housing units) will need to get the
developer’s endorsement on their deeds of assignment when these purchaser
sell off their properties to others. The need to get the developer’s
endorsement arises because at that point in time, the strata title (or the
qualified title as the case may be) has yet to be issued.
16.2
In Lim Seang Mee v Keepahead Holdings Sdn Bhd
[1993] 2 AMR 51:3553, the issue
before Mohamed Zaiddin J. was whether the developer’s practice of charging
an exorbitant sum of RM2,000 as “administrative fee” should be allowed. It
was submitted by counsel for the purchasers that the 1966 Act as well as
the 1989 Regulations “do not provide for the payment of any administrative
fee”. Counsel for the developer submitted that the developer is under no
legal obligation to endorse the deed of assignment nor to give a letter of
undertaking to the new purchaser. Consequently, he argued that it was
lawful and reasonable for the developer to demand the sum from the
purchaser. The court held that “a fair and reasonable amount should be a
sum of RM500.”
On November 1, 1993, the
Supreme Court, in an oral judgement, upheld the decision of the trial
Judge. It remains to be seen, even as of today, when (if ever) the
Ministry of Housing will act to update the Regulations in line with the
judicial recommendation.
16.3
In Singapore, its Housing Developers Rules 1976 (amended in 1981)
stipulated that the maximum amount which the developers may charge as
administrative costs is S$200.
17 DELAY IN COMPLETION
17.1
The standard SPA provides that if the developer fails to complete
the house within the stipulated time, the purchaser is entitled to claim
“liquidated damages to be calculated from day to day at the rate of ten
per centum (10%) per annum of the purchase price” (see Clause 20(2) of
Schedule G and 22(2) of Schedule H). The inevitable question for the
purchaser is: “What happens if I lose more than that amount? Can I claim
my actual loss?”
17.2
Case law does not seem to side with the purchaser on this point. In
Limmewah Development Sdn Bhd v Dr Jasbir Singh [1993] 2 AMR
1263, the house which should have been handed over to the purchaser on 25
August 1981 was only completed in January 1985. When the purchaser sued
the developer the actual loss and expense which he incurred as a result of
the long delay, the trial Judge (Richard Talalla J.) held that in view of
the remedy provided under the Act, he cannot recover anything further or
beyond it.
18 DEFECTIVE HOUSING
18.1
Examples of defective houses arising from poor construction work
are legion. An example often cited is a major housing project, consisting
of 1,800 low-cost flats and terrace houses at Bandar Indera Mahkota,
Pahang, undertaken by the Pahang State Economic Development Corporation.
The contractor for the project was a joint-venture company set up by the
Pahang SEDC and a South Korean company. Soon after the housing project was
completed, complaints started surfacing – cracked walls and floors,
collapsing door frames, generally shoddy workmanship, sub-standard
building materials, cement bags and styrofoam stuffed into walls instead
of bricks, and shoddy wiring which short-circuited when rain water seeped
in. The project was ultimately condemned as unsafe and the residents were
resettled by the SEDC.
18.2
Several quarters (including this writer) have suggested to the
authorities to consider enacting a legislation similar to the United
Kingdom Defective Premises Act 1972 (see previous page). The Housing and
Local Government Ministry has (so far) not indicated whether it is
prepared to introduce such a legislation in the near (or distant) future.
Complaints
18.3
Usual complaints include –
(a) shoddy workmanship;
(b) late delivery;
(c) late issuance of CF;
(d) no water and electricity connection;
(e)
poor infrastructure works at site;
(f)
houses not built according to specifications or in contravention of
current regulations.
18.3 Attempts have been made to resolve these complaints – with varying degrees
of success. Remedial steps taken include requiring developers to
submit statements and progress reports every six months, and ad hoc site
inspections by Ministry officials. FOMCA receives 40,000 complaints from
house buyers every year [NST 2/2/2000], and the number is still
increasing. In related moves, the Institute of Construction Quality
Control (ICQC) had been established, likewise the new House Buyers Association (HBA). The Housing
Developers Association had also established their Housing Complaints
Tribunal.
18.4 A
promising sign surfaced in February 1997 when the Housing Minister
announced the federal government’s offer to provide incentives to
developers to build “zero
defect” houses. It was announced that a technical committee had been set up to draw up guidelines
for the scheme and that the types of
incentives offered would be made known later.
PART TWO – FUTURE OUTLOOK: IS IT GOING TO BE ANY
BETTER?
18
EARLIER PROPOSALS
18.1
Various proposals have been put forward by several quarters in an
attempt to address the problem of housing defects as well as developer’s
delay. Some of the proposals are –
(a) a colour-coded demerit system
(NST 2/2/2000); [apparently, now shelved]
(b)
black-listing developers; [In fact, this has long been implemented.
As of July 1999, 27 developers had been black-listed by the Housing
Ministry – NST 18/2/2000]
(c)
blacklisting individuals managing house developing companies;
(d)
setting up a data bank of such individuals based on their track
record.
18.2
There are also other proposals mentioned (as 31st
December 1999) –
(a)
Uniform Building By-Laws 1984 to be amended – under which CF will
be deemed issued in 2 weeks from the date the developer submits his
application to the local authorities; mandatory for developers to get CF
before handing over vacant possession of house to purchasers. [Note that
as far back as 1997, the Cabinet had directed that all local authorities
must issue the CF within 14 days once the developer has met all structural
and legal requirements].
(b)
Housing Minister urged all states to gazette early amendments of
the 1984 By-Laws so that CF can be issued within 2 weeks.
(c)
The Cabinet urged developers to play their “social role” by e.g.
providing amenities for the handicapped, and building low-cost houses with
3 rooms (UM 16/8/99).
(d)
Housing Minister announced that the existing penalties will be
increased for offences committed by developers “against unsuspecting
purchasers.” [More of this later].
(e)
Housing Minister announced that the 1966 Act will be extended to
cover statutory bodies and co-operative societies. [Proposal now contained
in the Amendment Act]
19
ENSURING OPEN SPACES
19.1
When purchasers buy properties in a housing estate, they expect
that open spaces and recreational areas (as designated in the housing
estate’s layout plan at the time of purchase) will remain as they are over
time. However, in several housing projects, this was not the case. The
open areas were subsequently alienated, sometimes to the same developer
and at other times to some enterprising applicants. What was a green lung
yesterday can turn into a multi-storey apartment today (see New Straits
Times, July 25,1994). Reports from several states, including Selangor,
show that “continuity of open spaces” in housing estates cannot be taken
for granted.
19.2 In the face of increasing complaints by distressed house owners,
the Housing Minister finally took action in March 1997 to request all
state governments to discontinue the practice of degazetting such open
spaces and turning them into development sites. Commenting on this, the
Chief Minister of Penang was quoted as saying that he would “heed the
Ministry’s advice” but he wanted concrete and clearer guidelines.
19.3 In Selangor, the (previous) Menteri Besar acknowledged that land
officers sometimes “overlooked” the nature of these open spaces and
approved applications for development projects without realizing that the
open areas had been gazetted for other purposes, such as recreation. He
agreed that open spaces must be left in their present state and that land
officers “must automatically reject applications to develop them”. Asked
to comment about a particular case in Subang Jaya, where approval had been
given to build a condominium project at a playground, the Menteri Besar
admitted that it was a mistake and said the matter had been duly
rectified. (New Straits Times, February 19, 1997).
20
PRESERVING THE ENVIRONMENT
20.1
Housing development undertaken on hill-slopes and mountain-slopes
(referred to as ‘hillside developments’) have in the past been permitted
by local authorities. The effect, at times, had been catastrophic. This
state of affairs actually made a mockery of the Land Conservation Act 1960
– see in particular section 6 (restriction against clearing and
development) and section 11 (control of silt and erosion).
20.2
Despite the tragic incident involving the Highland Towers in Ampang
(the decision of the Kuala Lumpur High Court is still pending appeal) and
the collapse of newly-constructed buildings in Cameron Highlands some time
ago, it seems that some people never learn. The urge to tamper with nature
and disturb the eco-system appears to continue unabated. A case in point a
little while ago was the proposal to develop Bukit Larut in Taiping (since
abandoned).
20.3
As a result of intervention by the Prime Minister, the days of
hillside developments are probably now over. In March 1997, while on a
return flight from Kuantan to Kuala Lumpur, the Prime Minister saw massive
hillside development being carried out in an area in Selangor. That
incident led to the Prime Minister issuing a directive to curb such
development. Local authorities have been told not to grant any approvals
for housing projects where trees had to be cut, and hills and mountains
leveled / flattened. In cases where approvals had already been given,
local authorities were instructed to liaise with the developers to make
the necessary changes to the development orders or approvals.
20.4
In a related move, the Ministry of Housing and Local Government had
also directed local authorities to assign officials to conduct checks and
physically inspect proposed development sites to ascertain for themselves
the topography of the land in question before granting any approval to the
developer. Following a Cabinet decision on the matter, the Ministry had
also prepared and issued guidelines for developers on the preservation of
topography and vegetation.
21
SUBSEQUENT PROPOSALS
21.1
Before we take a look at the Amendment Act you might want to
reflect on a handful of other “interesting suggestions” put forward by
several quarters.
(a)
Developers will be required to part-finance the construction of
access roads to the main road – Works Ministry idea [NST 9/2/2000];
(b)
Housing Ministry will post details of housing developers and their
approved projects in the Ministry website [NST 25/1/2000];
(c)
There is a long-term plan to enable developers to submit
e-applications through the Internet;
(d)
A new law (Building Common Properties Act) will be tabled in
Parliament, to draw the “lines of responsibility” for managers of condos
and apartments [NST 29/1/2000];
(e)
A new body known as MAHSURI (Malaysian Human Settlements and
Urbanisation Research Institute) will be set up.
22
THE 2001 AMENDMENT ACT
Overview
22.1
The Amendment Act contains 26 sections. The name of principal Act
is now changed to The Housing Development (Control and Licensing) Act
1966. The Act is also given a new format. It is now divided into 7
distinct parts as follows-
Part I Preliminary
(covering sections 1 to 4)
Part II Licensing Housing
Developers (covering sections 5 to 6)
Part III Duties of a licensed Housing
Developer (covering sections 7 to 9)
Part IV Investigation and
Enforcement (covering section 10)
Part V Powers of the Minister
(covering section 11 to 16)
Part VI Tribunal for Homebuyer Claims
(covering new sections 16A to 16AI)
Part VII Miscellaneous
(covering sections 17 to 19)
22.1 The
existing section 2(1) of the principal Act has been deleted. Consequently,
the new law applies to statutory bodies and co-operative societies.
Section 4 has been amended to empower the Minister to appoint Deputy
Controllers of Housing and other officers. It also enables the Controller
to delegate his functions.
22.2
Section 5 is amended to require the payment of fees to the
Controller when an application for a developer’s licence is made. Section
6 is amended to require the payment of a minimum deposit of RM250,000 by a
company applying for a licence. The deposit payable by “a person or a body
of persons” (currently at RM100,000) has been increased to RM200,000. The
deposit is to be kept until the expiry of the defects liability period
(new section 6A).
22.3
The new law also enables the Controller to forfeit the deposit in
certain cases – e.g. when the developer is behaving in a manner
“detrimental to the interest of the purchasers or to any member of the
public”, has insufficient assets to cover his liabilities, has contravened
any provisions of the Act or has ceased business operations (new section
6B). Before doing so, however, the Controller must give the developer an
opportunity to state his case.
22.4
Section 7 of the principal Act (which deals with the duties of a
housing developer) has been amended by the addition of paragraphs (h) to (k),
resulting in enlarging the scope of such duties. The net effect of this
amendment is to ensure that the purchasers can get their CF early, the
issuance of separate or strata titles and the transfer of such titles to
them.
22.5
Section 7A (which deals with Housing Development Account) has been
amended to enhance the penalties five-fold for developers contravening
this section.
22.6
A new section 7B has been added, which states that a licensed
developer (for purposes of being given directions by the Minister) shall
include “any housing developer whose licence has expired.”
22.7
The existing section 8 has been amended to require a housing
developer to notify the Controller when he enters into any arrangement or
agreement which affects its management or business.
22.8
A new section 8A has been added, which provides for the statutory
termination of the sale and purchase agreement (SPA). It sets out the
conditions and procedures for making applications under this new section.
Essentially what is contemplated under this new section is that if after 6
months of the SPA the project has not commenced and if at least 75% of all
the purchasers who had signed the SPA wish to terminate the SPA, the
developer can apply to the Minister to have the SPA terminated. The
Minister has the discretion whether to approve or refuse the application.
If approved, he can impose such conditions as he may deem fit and proper.
The decision is final and cannot be questioned in a court of law, and is
binding on all the purchasers and the developer. All monies received must
be refunded free of interest within the period as stipulated by the
Minister. Upon receipt of the refund, all encumbrances must be removed,
and all costs and expenses incurred shall be borne by the developer
(recoverable as a civil debt). Failure to comply with this section is an
offence, punishable with fine not exceeding RM50,000, and a daily fine of
not exceeding RM5000.
22.9
Under a new Part IV (dealing with investigation and enforcement),
new sections 10A to 10J have been added. These confer powers of entry,
search and seizure (section 10A), search of person (section 10B), and
examination of persons (section 10E).
22.10
Section 11 (which enables the Minister to give special directions)
has been amended to enable the Minister to certify that a licensed housing
developer has abandoned his project.
22.11
A new section 13A is added to the principal Act, under which the
Controller is now empowered to lodge a report on the conduct of an
architect or engineer to this respective professional body in the event
that such conduct “has prejudiced the interest of the purchaser”.
22.12
Under a new section 13B, a housing developer’s licence cannot be
transferred or assigned. All such transfers and assignments “shall be
void”.
22.13
The Tribunal for Homebuyers Claims
(a)
Under a new Part VI, the new law established the Tribunal For
Homebuyer Claims. The Tribunal consists of a Chairman and a Deputy
Chairman (to be appointed by the Housing Minister from the members of the
Judicial and Legal Service, in other words, someone from the courts or
from the Attorney-General’s Chambers) and not less than 5 other members.
For the latter posts, the Minister can choose whether to appoint someone
from the Judicial and Legal Service or from the roll of advocates and
solicitors in the country having 7 years standing in the profession.
Tenure of office shall not exceed 3 years but everyone is eligible for
reappointment up to three consecutive terms.
(b)
Like always, the Minister has the power to hire and fire. Section
16F empowers him to revoke the appointment of any member of the Tribunal
on various grounds – e.g. misconduct, incapable of discharging his duties,
conviction of offences involving fraud, dishonesty or moral turpitude. A
member can also resign at any time by giving 3 months notice in writing to
the Minister.
(c)
Section 16E states that the “The Tribunal may sit” (in other words
it can be convened) “in one or more sittings” at any time and at such
place as the Chairman may determine.
(d)
Under section 16L, proceedings are said to commence when a
homebuyer lodges a claim “in the prescribed form together with the
prescribed fee” in which he claims “any loss suffered or any matter
concerning his interests as a homebuyer under this Act”. Under section
16M(4), a homebuyer’s claim “may include loss or damage of a consequential
nature”. The actual meaning of this subsection is a matter of some doubt
and conjecture. We will have to wait for an actual case coming up before
the Tribunal before we can say with some certainty what kind of
“consequential loss” can be claimed against a developer.
(e)
Whilst the establishment of the Tribunal is warmly welcomed, some
quarters feel unhappy about the low limit imposed on the claim. Under
section 16M(1), no claim can be made in excess of RM25,000. When queried
on this point in the Dewan Rakyat recently, the Housing Minister replied
that claims exceeding the limit can still be filed in court. He pointed
that homebuyers are therefore not deprived of their remedies against the
developer. [There is a way to get around the RM25,000 limit. If both
parties (the developer and the homebuyer) mutually agree to allow the
Tribunal to hear a claim involving a sum exceeding that amount, the
Tribunal can still do so – see section 16O(1). Such an agreement, however, must
be in writing and preferable should be made before a claim is lodged with
the Tribunal – see section 16O(2)(a).]
(f)
If a homebuyer has filed a claim exceeding RM25,000 and the
developer cannot be persuaded to agree to allow the Tribunal to hear the
claim, the Tribunal still has jurisdiction to hear the claim if the
homebuyer then decides to abandon (forego) that portion of the claim in
excess of the RM25,000.
(g)
There are also procedural matters which homebuyers must keep in
mind. Under section 16N(s), the claim must be filed with the Tribunal not
later than 12 months of the issuance of the CF or the expiry date of the
defects liability period (DLP). The draft Amendment Bill at this point,
however, makes no mention whether it is “whichever is earlier” or
“whichever is later”.
(h)
When a homebuyer has already filed his claim against the developer
with the Tribunal, he is no longer permitted to file the same claim
against the developer in the courts – section 16R. Once the claim has been
filed, the Secretary to the Tribunal will then notify the parties (the
homebuyer and the developer) the day, time and place of the hearing –
section 16S.
(i)
Under section 16T(1), the Tribunal has the power to make an
assessment of the case with a view of deciding whether it is appropriate
for it to “assist the parties” to work out an amicable settlement. If an
agreed settlement can be reached by the homebuyer and the developer, the
Tribunal will record the settlement, whereupon it will “take effect as if
it were an award of the Tribunal” – section 16T(3)
(j)
|